10th of Ramadan PWTP

Sharquia Governorate Greater Cairo, Egypt

Project Info

Client

CAPW - Construction Authority for Potable Water and Wastewater 44 Ramsis Street - Cairo

Project Type

Turn Key Project

Completed

10/2009 – 07/2013

General Contractor

Bamag Mena LLC

Capacity

600.000 m3 / Day

Execution Time

36 month

Operation Time

12 month

Operation Time

12 month

Process

Potable Water Treatment

Details

Process design, electromechanical supply, installation, commissioning and operation of PWTP with Intake and booster pumping station with Capacity of 600.000 m³/d, potable water.